| | Furniture Replacement | $3,800,000.00 | $3,372,912.00 | $-427,088.00 | Complete |
|
| Adams Hill ES | Admin Upgrade | $6,300,000.00 | $3,606,039.00 | $-2,693,961.00 | Complete |
|
| Boone ES | Window/ADA Upgrades | $75,000.00 | $.00 | $-75,000.00 | Complete |
|
| Brandeis HS | Athletic Upgrades | $2,675,000.00 | $2,410,307.00 | $-264,693.00 | Complete |
|
| Brennan HS | Athletic Upgrades | $1,374,600.00 | $.00 | $-1,374,600.00 | Complete |
|
| Cable ES | ALE Upgrades | $2,900,000.00 | $2,390,968.00 | $-509,032.00 | Complete |
|
| Cable ES | Window/ADA Upgrades | $625,000.00 | $130,308.00 | $-494,692.00 | Complete |
|
| Clark HS | Athletic Upgrades | $1,644,600.00 | $1,333,917.00 | $-310,683.00 | Complete |
|
| Clark HS | Athletic Upgrades | $295,000.00 | $267,037.00 | $-27,963.00 | Complete |
|
| Clark HS | HS Vent Hood Replacements | $1,330,000.00 | $640,737.00 | $-689,263.00 | Complete |
|
| Cody ES | Bus Student Covered Walkways | $700,000.00 | $570,690.00 | $-129,310.00 | Complete |
|
| Connally MS | Athletic Upgrades | $440,000.00 | $521,822.00 | $81,822.00 | Complete |
|
| Elrod ES | Cafeteria Upgrade/Renovations | $3,000,000.00 | $3,228,431.00 | $228,431.00 | Complete |
|
| Elrod ES | Kiln Upgrade | $600,000.00 | $511,165.00 | $-88,835.00 | Complete |
|
| Esparza ES | ALE Upgrades | $2,800,000.00 | $1,993,768.00 | $-806,232.00 | Complete |
|
| Esparza ES | Window/ADA Upgrades | $350,000.00 | $221,407.00 | $-128,593.00 | Complete |
|
| Farris Stadium | Athletic Upgrades | $700,000.00 | $537,239.00 | $-162,761.00 | Complete |
|
| Glass ES | ALE Upgrades | $2,800,000.00 | $2,309,418.00 | $-490,582.00 | Complete |
|
| Glass ES | Cafeteria/Gym Upgrade | $14,800,000.00 | $15,093,051.00 | $293,051.00 | Complete |
|
| GlenOaks ES | Classroom Upgrade/Renovations | $5,700,000.00 | $4,750,978.00 | $-949,022.00 | Complete |
|
| Hardin Athletic Complex | Athletic Upgrades | $3,000,000.00 | $1,988,904.00 | $-1,011,096.00 | Complete |
|
| Harlan HS | Athletic Upgrades | $1,270,000.00 | $.00 | $-1,270,000.00 | Complete |
|
| Health Careers HS | Athletic Upgrades | $219,200.00 | $48,875.00 | $-170,325.00 | Complete |
|
| Health Careers HS | HS Vent Hood Replacements | $325,000.00 | $205,361.00 | $-119,639.00 | Complete |
|
| Hobby MS | Athletic Upgrades | $455,000.00 | $465,971.00 | $10,971.00 | Complete |
|
| Hobby MS | Bus Student Covered Walkways | $2,900,000.00 | $1,434,660.00 | $-1,465,340.00 | Complete |
|
| Hobby MS | Science Labs | $7,400,000.00 | $4,486,454.00 | $-2,913,546.00 | Complete |
|
| Holmes HS | Athletic Upgrades | $1,489,000.00 | $.00 | $-1,489,000.00 | Complete |
|
| Holmes HS | Athletic Upgrades | $20,000,000.00 | $5,000,000.00 | $-15,000,000.00 | Complete |
|
| Holmes HS | Classroom Addition/Replacement | $28,800,000.00 | $12,713,121.00 | $-16,086,879.00 | Complete |
|
| Holmes HS | HS Vent Hood Replacements | $1,400,000.00 | $573,730.00 | $-826,270.00 | Complete |
|
| Holmes HS | Paint Booth Replacements | $400,000.00 | $217,856.00 | $-182,144.00 | Complete |
|
| Jay HS | Athletic Upgrades | $280,000.00 | $234,033.00 | $-45,967.00 | Complete |
|
| Jay HS | Auditorium Replacement | $47,800,000.00 | $50,320,834.00 | $2,520,834.00 | Complete |
|
| Jay HS | HS Vent Hood Replacements | $1,245,000.00 | $750,118.00 | $-494,882.00 | Complete |
|
| Jay HS | Paint Booth Replacements | $400,000.00 | $214,986.00 | $-185,014.00 | Complete |
|
| Jefferson MS | Athletic Upgrades | $460,000.00 | $459,091.00 | $-909.00 | Complete |
|
| Jones MS | Athletic Upgrades | $440,000.00 | $543,464.00 | $103,464.00 | Complete |
|
| Jordan MS | Athletic Upgrades | $425,000.00 | $338,423.00 | $-86,577.00 | Complete |
|
| Knowlton ES | Fire Sprinkler System | $1,100,000.00 | $657,069.00 | $-442,931.00 | Complete |
|
| Leon Valley ES | Admin Upgrade | $7,700,000.00 | $5,221,951.00 | $-2,478,049.00 | Complete |
|
| Leon Valley ES | Fire Sprinkler System | $800,000.00 | $676,970.00 | $-123,030.00 | Complete |
|
| Leon Valley ES | Window/ADA Upgrades | $345,000.00 | $239,477.00 | $-105,523.00 | Complete |
|
| Linton ES | Window/ADA Upgrades | $805,000.00 | $818,245.00 | $13,245.00 | Complete |
|
| Luna MS | Athletic Upgrades | $460,000.00 | $459,733.00 | $-267.00 | Complete |
|
| Luna MS | Science Labs | $5,500,000.00 | $4,154,245.00 | $-1,345,755.00 | Complete |
|
| Marshall HS | Athletic Upgrades | $295,000.00 | $.00 | $-295,000.00 | Complete |
|
| Marshall HS | Athletic Upgrades | $1,497,200.00 | $.00 | $-1,497,200.00 | Complete |
|
| Marshall HS | HS Vent Hood Replacements | $1,200,000.00 | $1,037,315.00 | $-162,685.00 | Complete |
|
| Marshall LMS Magnet HS | CTE Upgrade | $45,000,000.00 | $27,423,010.00 | $-17,576,990.00 | Complete |
|
| Mary Hull ES | Library Additions/Upgrades | $1,800,000.00 | $1,014,716.00 | $-785,284.00 | Complete |
|
| Meadow Village ES | ALE Upgrades | $2,100,000.00 | $1,558,985.00 | $-541,015.00 | Complete |
|
| Multiple Sites | Shades Over Playgrounds | $2,951,390.00 | $1,952,727.00 | $-998,663.00 | Complete |
|
| Multiple Sites | Shades Over Playgrounds | $3,248,610.00 | $3,235,227.00 | $-13,383.00 | Complete |
|
| Neff MS | Athletic Upgrades | $455,000.00 | $403,970.00 | $-51,030.00 | Complete |
|
| Neff MS | Cafeteria Upgrade/Renovations | $5,900,000.00 | $5,542,403.00 | $-357,597.00 | Complete |
|
| Northwest Crossing ES | Cafeteria Upgrade/Renovations | $2,800,000.00 | $2,749,889.00 | $-50,111.00 | Complete |
|
| O'Connor HS | Ag Facility Upgrade | $1,600,000.00 | $719,557.00 | $-880,443.00 | Complete |
|
| O'Connor HS | Athletic Upgrades | $1,390,200.00 | $79,853.00 | $-1,310,347.00 | Complete |
|
| O'Connor HS | Athletic Upgrades | $285,000.00 | $234,025.00 | $-50,975.00 | Complete |
|
| Passmore ES | Library Additions/Upgrades | $1,800,000.00 | $1,203,974.00 | $-596,026.00 | Complete |
|
| Pease MS | Athletic Upgrades | $440,000.00 | $545,121.00 | $105,121.00 | Complete |
|
| Powell ES | Cafeteria/Gym Upgrade | $11,000,000.00 | $10,431,516.00 | $-568,484.00 | Complete |
|
| Rawlinson MS | Athletic Upgrades | $440,000.00 | $409,418.00 | $-30,582.00 | Complete |
|
| Rayburn MS | Athletic Upgrades | $290,000.00 | $230,780.00 | $-59,220.00 | Complete |
|
| Rayburn MS | Fine Arts | $3,300,000.00 | $2,856,416.00 | $-443,584.00 | Complete |
|
| Rhodes ES | Bus Student Covered Walkways | $700,000.00 | $1,590,970.00 | $890,970.00 | Complete |
|
| Ross MS | Athletic Upgrades | $455,000.00 | $350,501.00 | $-104,499.00 | Complete |
|
| Rudder MS | Athletic Upgrades | $425,000.00 | $342,571.00 | $-82,429.00 | Complete |
|
| Rudder MS | Cafeteria Upgrade/Renovations | $5,200,000.00 | $3,849,833.00 | $-1,350,167.00 | Complete |
|
| Stevens HS | Athletic Upgrades | $1,450,000.00 | $.00 | $-1,450,000.00 | Complete |
|
| Stevenson MS | Athletic Upgrades | $425,000.00 | $342,233.00 | $-82,767.00 | Complete |
|
| Stevenson MS | Gym/Athletic Upgrades | $18,500,000.00 | $9,399,290.00 | $-9,100,710.00 | Complete |
|
| Stinson MS | Athletic Upgrades | $440,000.00 | $348,308.00 | $-91,692.00 | Complete |
|
| Taft HS | Athletic Upgrades | $1,500,000.00 | $212,102.00 | $-1,287,898.00 | Complete |
|
| Taft HS | Athletic Upgrades | $565,000.00 | $489,537.00 | $-75,463.00 | Complete |
|
| Taft HS | Library Additions/Upgrades | $5,600,000.00 | $4,384,503.00 | $-1,215,497.00 | Complete |
|
| Timberwilde ES | Fire Sprinkler System | $500,000.00 | $364,679.00 | $-135,321.00 | Complete |
|
| Vale MS | Athletic Upgrades | $440,000.00 | $372,115.00 | $-67,885.00 | Complete |
|
| Warren HS | Athletic Upgrades | $1,450,200.00 | $68,438.00 | $-1,381,762.00 | Complete |
|
| Westwood Terrace ES | Classroom Addition/Replacement | $15,400,000.00 | $11,119,459.00 | $-4,280,541.00 | Complete |
|
| Zachry MS | Athletic Upgrades | $290,000.00 | $328,150.00 | $38,150.00 | Complete |
|