| Furniture Replacement | $3,800,000.00 | $3,800,000.00 | $.00 | |
|
Adams Hill ES | Admin Upgrade | $6,300,000.00 | $3,743,561.00 | $-2,556,439.00 | Complete |
|
Boone ES | Window/ADA Upgrades | $75,000.00 | $.00 | $-75,000.00 | Complete |
|
Brandeis HS | Athletic Upgrades | $2,675,000.00 | $2,410,307.00 | $-264,693.00 | Complete |
|
Brennan HS | Athletic Upgrades | $1,374,600.00 | $.00 | $-1,374,600.00 | Complete |
|
Cable ES | ALE Upgrades | $2,900,000.00 | $2,900,000.00 | $.00 | Under Construction |
|
Cable ES | Window/ADA Upgrades | $625,000.00 | $625,000.00 | $.00 | Under Construction |
|
Clark HS | Athletic Upgrades | $1,644,600.00 | $1,333,919.00 | $-310,681.00 | Complete |
|
Clark HS | Athletic Upgrades | $295,000.00 | $267,038.00 | $-27,962.00 | Complete |
|
Clark HS | HS Vent Hood Replacements | $1,330,000.00 | $640,737.00 | $-689,263.00 | Complete |
|
Cody ES | Bus Student Covered Walkways | $700,000.00 | $570,691.00 | $-129,309.00 | Complete |
|
Connally MS | Athletic Upgrades | $440,000.00 | $523,403.00 | $83,403.00 | Complete |
|
Elrod ES | Cafeteria Upgrade/Renovations | $3,000,000.00 | $3,238,219.00 | $238,219.00 | Under Construction |
|
Elrod ES | Kiln Upgrade | $600,000.00 | $600,000.00 | $.00 | Under Construction |
|
Esparza ES | ALE Upgrades | $2,800,000.00 | $2,800,000.00 | $.00 | Under Construction |
|
Esparza ES | Window/ADA Upgrades | $350,000.00 | $350,000.00 | $.00 | Under Construction |
|
Farris Stadium | Athletic Upgrades | $700,000.00 | $537,240.00 | $-162,760.00 | Complete |
|
Glass ES | ALE Upgrades | $2,800,000.00 | $3,930,000.00 | $1,130,000.00 | Complete |
|
Glass ES | Cafeteria/Gym Upgrade | $14,800,000.00 | $14,802,123.00 | $2,123.00 | Bidding |
|
GlenOaks ES | Classroom Upgrade/Renovations | $5,700,000.00 | $4,728,681.00 | $-971,319.00 | Complete |
|
Hardin Athletic Complex | Athletic Upgrades | $3,000,000.00 | $1,988,905.00 | $-1,011,095.00 | Complete |
|
Harlan HS | Athletic Upgrades | $1,270,000.00 | $1,270,000.00 | $.00 | Complete |
|
Health Careers HS | Athletic Upgrades | $219,200.00 | $219,200.00 | $.00 | Complete |
|
Health Careers HS | HS Vent Hood Replacements | $325,000.00 | $205,361.00 | $-119,639.00 | Complete |
|
Hobby MS | Athletic Upgrades | $455,000.00 | $541,334.00 | $86,334.00 | Under Construction |
|
Hobby MS | Bus Student Covered Walkways | $2,900,000.00 | $1,434,661.00 | $-1,465,339.00 | Complete |
|
Hobby MS | Science Labs | $7,400,000.00 | $7,400,000.00 | $.00 | Under Construction |
|
Holmes HS | Athletic Upgrades | $1,489,000.00 | $.00 | $-1,489,000.00 | Complete |
|
Holmes HS | Athletic Upgrades | $20,000,000.00 | $20,000,000.00 | $.00 | Complete |
|
Holmes HS | Classroom Addition/Replacement | $28,800,000.00 | $28,800,000.00 | $.00 | Bidding |
|
Holmes HS | HS Vent Hood Replacements | $1,400,000.00 | $573,730.00 | $-826,270.00 | Complete |
|
Holmes HS | Paint Booth Replacements | $400,000.00 | $217,856.00 | $-182,144.00 | Complete |
|
Jay HS | Athletic Upgrades | $280,000.00 | $234,033.00 | $-45,967.00 | Complete |
|
Jay HS | Auditorium Replacement | $47,800,000.00 | $56,200,000.00 | $8,400,000.00 | Under Construction |
|
Jay HS | HS Vent Hood Replacements | $1,245,000.00 | $1,245,000.00 | $.00 | Under Construction |
|
Jay HS | Paint Booth Replacements | $400,000.00 | $213,703.00 | $-186,297.00 | Complete |
|
Jefferson MS | Athletic Upgrades | $460,000.00 | $544,334.00 | $84,334.00 | Under Construction |
|
Jones MS | Athletic Upgrades | $440,000.00 | $546,445.00 | $106,445.00 | Complete |
|
Jordan MS | Athletic Upgrades | $425,000.00 | $338,514.00 | $-86,486.00 | Complete |
|
Knowlton ES | Fire Sprinkler System | $1,100,000.00 | $654,067.00 | $-445,933.00 | Complete |
|
Leon Valley ES | Admin Upgrade | $7,700,000.00 | $7,712,315.00 | $12,315.00 | Under Construction |
|
Leon Valley ES | Fire Sprinkler System | $800,000.00 | $676,972.00 | $-123,028.00 | Complete |
|
Leon Valley ES | Window/ADA Upgrades | $345,000.00 | $345,000.00 | $.00 | Under Construction |
|
Linton ES | Window/ADA Upgrades | $805,000.00 | $921,000.00 | $116,000.00 | Under Construction |
|
Luna MS | Athletic Upgrades | $460,000.00 | $544,334.00 | $84,334.00 | Under Construction |
|
Luna MS | Science Labs | $5,500,000.00 | $4,153,558.00 | $-1,346,442.00 | Complete |
|
Marshall HS | Athletic Upgrades | $295,000.00 | $.00 | $-295,000.00 | Under Construction |
|
Marshall HS | Athletic Upgrades | $1,497,200.00 | $.00 | $-1,497,200.00 | Complete |
|
Marshall HS | HS Vent Hood Replacements | $1,200,000.00 | $1,037,316.00 | $-162,684.00 | Complete |
|
Marshall LMS Magnet HS | CTE Upgrade | $45,000,000.00 | $45,388,120.00 | $388,120.00 | Under Construction |
|
Mary Hull ES | Library Additions/Upgrades | $1,800,000.00 | $1,900,000.00 | $100,000.00 | Under Construction |
|
Meadow Village ES | ALE Upgrades | $2,100,000.00 | $1,558,987.00 | $-541,013.00 | Complete |
|
Multiple Sites | Shades Over Playgrounds | $2,951,390.00 | $2,951,390.00 | $.00 | Under Construction |
|
Multiple Sites | Shades Over Playgrounds | $3,248,610.00 | $3,483,868.00 | $235,258.00 | Under Construction |
|
Neff MS | Athletic Upgrades | $455,000.00 | $403,971.00 | $-51,029.00 | Complete |
|
Neff MS | Cafeteria Upgrade/Renovations | $5,900,000.00 | $5,937,928.00 | $37,928.00 | Complete |
|
Northwest Crossing ES | Cafeteria Upgrade/Renovations | $2,800,000.00 | $2,737,453.00 | $-62,547.00 | Complete |
|
O'Connor HS | Ag Facility Upgrade | $1,600,000.00 | $716,128.00 | $-883,872.00 | Complete |
|
O'Connor HS | Athletic Upgrades | $1,390,200.00 | $79,853.00 | $-1,310,347.00 | Complete |
|
O'Connor HS | Athletic Upgrades | $285,000.00 | $234,025.00 | $-50,975.00 | Complete |
|
Passmore ES | Library Additions/Upgrades | $1,800,000.00 | $1,800,000.00 | $.00 | Complete |
|
Pease MS | Athletic Upgrades | $440,000.00 | $547,974.00 | $107,974.00 | Complete |
|
Powell ES | Cafeteria/Gym Upgrade | $11,000,000.00 | $11,779,781.00 | $779,781.00 | Under Construction |
|
Rawlinson MS | Athletic Upgrades | $440,000.00 | $412,301.00 | $-27,699.00 | Complete |
|
Rayburn MS | Athletic Upgrades | $290,000.00 | $230,780.00 | $-59,220.00 | Complete |
|
Rayburn MS | Fine Arts | $3,300,000.00 | $3,419,000.00 | $119,000.00 | Complete |
|
Rhodes ES | Bus Student Covered Walkways | $700,000.00 | $1,260,000.00 | $560,000.00 | Bidding |
|
Ross MS | Athletic Upgrades | $455,000.00 | $350,502.00 | $-104,498.00 | Complete |
|
Rudder MS | Athletic Upgrades | $425,000.00 | $342,572.00 | $-82,428.00 | Complete |
|
Rudder MS | Cafeteria Upgrade/Renovations | $5,200,000.00 | $3,831,767.00 | $-1,368,233.00 | Complete |
|
Stevens HS | Athletic Upgrades | $1,450,000.00 | $.00 | $-1,450,000.00 | Complete |
|
Stevenson MS | Athletic Upgrades | $425,000.00 | $342,234.00 | $-82,766.00 | Complete |
|
Stevenson MS | Gym/Athletic Upgrades | $18,500,000.00 | $18,500,000.00 | $.00 | Under Construction |
|
Stinson MS | Athletic Upgrades | $440,000.00 | $348,310.00 | $-91,690.00 | Complete |
|
Taft HS | Athletic Upgrades | $1,500,000.00 | $1,633,806.00 | $133,806.00 | Complete |
|
Taft HS | Athletic Upgrades | $565,000.00 | $489,538.00 | $-75,462.00 | Complete |
|
Taft HS | Library Additions/Upgrades | $5,600,000.00 | $5,600,000.00 | $.00 | Complete |
|
Timberwilde ES | Fire Sprinkler System | $500,000.00 | $503,397.00 | $3,397.00 | Complete |
|
Vale MS | Athletic Upgrades | $440,000.00 | $406,743.00 | $-33,257.00 | Complete |
|
Warren HS | Athletic Upgrades | $1,450,200.00 | $1,584,007.00 | $133,807.00 | Complete |
|
Westwood Terrace ES | Classroom Addition/Replacement | $15,400,000.00 | $15,585,992.00 | $185,992.00 | Complete |
|
Zachry MS | Athletic Upgrades | $290,000.00 | $334,499.00 | $44,499.00 | Complete |
|