| Adjacent to Sotomayor HS | New District Baseball/Softball | $23,700,000.00 | $12,783,247.00 | $-10,916,753.00 | Complete |
|
| Cable ES | Admin Suite/Classrooms Replacement | $21,800,000.00 | $33,100,000.00 | $11,300,000.00 | |
|
| Clark HS | Fine Arts Replacement | $56,900,000.00 | $81,119,494.00 | $24,219,494.00 | Under Construction |
|
| Colby Glass ES | Classrooms Replacement | $32,900,000.00 | $49,863,849.00 | $16,963,849.00 | |
|
| Colonies North ES | Cafeteria/Gym/Classrooms Replacement | $15,300,000.00 | $3,519,717.00 | $-11,780,283.00 | Complete |
|
| District-Wide Libraries | Library Modernization Package | $8,000,000.00 | $8,000,000.00 | $.00 | Bidding |
|
| Esparza ES | Cafeteria/Platform/Gym Replacement | $18,000,000.00 | $2,336,628.00 | $-15,663,372.00 | Complete |
|
| Glenoaks ES | Cafeteria/Platform/Gym Replacement | $15,900,000.00 | $24,500,000.00 | $8,600,000.00 | |
|
| Hobby MS | New Magnet Upgrades | $24,800,000.00 | $17,752,578.00 | $-7,047,422.00 | Complete |
|
| Holmes HS | Cafeteria/Kitchen/Athletics Replacement | $56,900,000.00 | $70,911,858.00 | $14,011,858.00 | Bidding |
|
| Jay HS | New SEA/ROTC/CTE/Parking | $55,800,000.00 | $71,508,577.00 | $15,708,577.00 | Under Construction |
|
| Jordan MS | New Magnet Upgrades | $17,400,000.00 | $7,773,869.00 | $-9,626,131.00 | Complete |
|
| Knowlton ES | ALE Upgrades | $3,000,000.00 | $3,000,000.00 | $.00 | Bidding |
|
| Marshall HS | Admin Suite/Classrooms Replacement | $30,000,000.00 | $43,859,290.00 | $13,859,290.00 | Under Construction |
|
| Mary Hull ES | Classrooms Replacement | $31,500,000.00 | $40,116,050.00 | $8,616,050.00 | |
|
| Meadow Village ES | Cafeteria/Platform/Gym/Classrooms Replacement
| $25,200,000.00 | $36,816,050.00 | $11,616,050.00 | |
|
| Multiple Sites | HS & MS Athletics/PE Locker/Flooring Upgrades | $4,500,000.00 | $2,783,827.00 | $-1,716,173.00 | Complete |
|
| Multiple Sites | HS Fume Hood Replacements | $5,400,000.00 | $7,190,844.00 | $1,790,844.00 | |
|
| Multiple Sites | New PE ES Sensory Play Area | $6,800,000.00 | $6,800,000.00 | $.00 | |
|
| Neff MS | Athletics & CTE Replacement | $30,000,000.00 | $8,931,626.00 | $-21,068,374.00 | Under Construction |
|
| O'Connor HS | Agri-Science Upgrades | $19,100,000.00 | $14,985,590.00 | $-4,114,410.00 | Complete |
|
| Powell ES | Admin Suite/Classrooms/Library Replacement | $21,300,000.00 | $32,400,000.00 | $11,100,000.00 | |
|
| Rayburn MS | Admin Suite Replacement | $14,400,000.00 | $11,648,101.00 | $-2,751,899.00 | Complete |
|
| Stevens HS | CAST TEACH Upgrades | $17,600,000.00 | $9,329,025.00 | $-8,270,975.00 | Complete |
|
| Stinson MS | New Magnet/ALE Upgrades | $19,900,000.00 | $19,930,830.00 | $30,830.00 | Under Construction |
|
| Sul Ross MS | Athletics Replacement | $24,900,000.00 | $3,489,458.00 | $-21,410,542.00 | Under Construction |
|
| Valley Hi ES | Classrooms Replacement | $27,000,000.00 | $43,396,838.00 | $16,396,838.00 | |
|
| Westwood Terrace ES | Cafeteria/Platform/Gym Replacement | $17,500,000.00 | $10,193,832.00 | $-7,306,168.00 | Complete |
|