Adjacent to Sotomayor HS | New District Baseball/Softball | $23,700,000.00 | $23,700,000.00 | $.00 | In Design |
|
Cable ES | Admin Suite/Classrooms Replacement | $21,800,000.00 | $21,800,000.00 | $.00 | In Design |
|
Clark HS | Fine Arts Replacement | $56,900,000.00 | $56,900,000.00 | $.00 | In Design |
|
Colby Glass ES | Classrooms Replacement | $32,900,000.00 | $32,900,000.00 | $.00 | |
|
Colonies North ES | Cafeteria/Gym/Classrooms Replacement | $15,300,000.00 | $20,300,000.00 | $5,000,000.00 | Under Construction |
|
District-Wide Libraries | Library Modernization Package | $8,000,000.00 | $8,000,000.00 | $.00 | |
|
Esparza ES | Cafeteria/Platform/Gym Replacement | $18,000,000.00 | $18,000,000.00 | $.00 | Under Construction |
|
Glenoaks ES | Cafeteria/Platform/Gym Replacement | $15,900,000.00 | $15,900,000.00 | $.00 | In Design |
|
Hobby MS | New Magnet Upgrades | $24,800,000.00 | $24,800,000.00 | $.00 | Under Construction |
|
Holmes HS | Cafeteria/Kitchen/Athletics Replacement | $56,900,000.00 | $56,900,000.00 | $.00 | In Design |
|
Jay HS | New SEA/ROTC/CTE/Parking | $55,800,000.00 | $55,800,000.00 | $.00 | In Design |
|
Jordan MS | New Magnet Upgrades | $17,400,000.00 | $17,400,000.00 | $.00 | Under Construction |
|
Knowlton ES | ALE Upgrades | $3,000,000.00 | $3,000,000.00 | $.00 | In Design |
|
Marshall HS | Admin Suite/Classrooms Replacement | $30,000,000.00 | $30,000,000.00 | $.00 | In Design |
|
Mary Hull ES | Classrooms Replacement | $31,500,000.00 | $31,500,000.00 | $.00 | |
|
Meadow Village ES | Cafeteria/Platform/Gym/Classrooms Replacement
| $25,200,000.00 | $25,200,000.00 | $.00 | |
|
Multiple Sites | HS & MS Athletics/PE Locker/Flooring Upgrades | $4,500,000.00 | $4,500,000.00 | $.00 | In Design |
|
Multiple Sites | HS Fume Hood Replacements | $5,400,000.00 | $6,646,564.00 | $1,246,564.00 | |
|
Multiple Sites | New PE ES Sensory Play Area | $6,800,000.00 | $6,800,000.00 | $.00 | |
|
Neff MS | Athletics & CTE Replacement | $30,000,000.00 | $30,000,000.00 | $.00 | Under Construction |
|
O'Connor HS | Agri-Science Upgrades | $19,100,000.00 | $19,100,000.00 | $.00 | Under Construction |
|
Powell ES | Admin Suite/Classrooms/Library Replacement | $21,300,000.00 | $21,300,000.00 | $.00 | In Design |
|
Rayburn MS | Admin Suite Replacement | $14,400,000.00 | $14,400,000.00 | $.00 | Under Construction |
|
Stevens HS | CAST TEACH Upgrades | $17,600,000.00 | $11,088,043.00 | $-6,511,957.00 | Complete |
|
Stinson MS | New Magnet/ALE Upgrades | $19,900,000.00 | $19,900,000.00 | $.00 | In Design |
|
Sul Ross MS | Athletics Replacement | $24,900,000.00 | $26,196,599.00 | $1,296,599.00 | Bidding |
|
Valley Hi ES | Classrooms Replacement | $27,000,000.00 | $27,000,000.00 | $.00 | |
|
Westwood Terrace ES | Cafeteria/Platform/Gym Replacement | $17,500,000.00 | $17,500,000.00 | $.00 | Under Construction |
|